The development will consist of:
• Demolition of an existing habitable house and an agricultural barn (total floor area c.599 sq.m).
• Construction of 239 no. dwellings comprising:
a) 136 no. 2-storey houses comprising 16 no. 2-bed, 114 no. 3-bed and 6 no.4-bed units;
b) 73 no. apartments within 3 no. 4-storey blocks comprising 29 no. 1-bed and 44 no. 2-bed units;
c) 30 no. duplex units within 3 no. 1-3 storey blocks comprising 15 no. 2-bed and 15 no. 3 bed units;
All with associated private gardens/ balconies/ terraces to the
north/south/east/west elevations.
• Construction of a creche (c. 294 sq.m) and a gym (c. 224 sq.m) at ground floor of Apartment Block A.
• 393 no. car parking spaces (including e-charging points) and 208 no. secure bike parking spaces located within dedicated bicycle stores.
• Vehicular access to the development via Leixlip Gate Avenue to the east with pedestrian/cyclist access via Leixlip Gate Avenue and the R449 to the west.
• Upgrading of part of Leixlip Gate Avenue which will entail modifications to the permitted boundary and vehicular access to the single dwelling permitted under KCC Reg. Ref.: 16/90.
• All associated site development works (including reprofiling/culverting of part of minor watercourse on site), provision of landscaped open spaces,boundary treatments, bin stores, ESB substation kiosks, public lighting; site services, drainage works (including foul pumping station on site and connection to existing foul sewer on Green Lane) and all associated infrastructure.
To find out more details on this Residential Development in Kildare Applied for on 2020-06-01 take the free trial here.